AMP² Daily Brief – November 4, 2026

AI. Money. Power.


The Neighbors Get a Vote

Voters in Ohio passed at least 14 local bans or restrictions on data centers on Tuesday, while the UK and Malaysia offered developers faster access in return for conditions. The money and the chips are still arriving, but who decides where AI gets built is changing.

Today’s Signals

  • Voters in at least 14 Ohio municipalities passed bans or restrictions on data centers in Tuesday’s election, according to unofficial results reported by The Columbus Dispatch.
  • Google plans to invest $15 billion in Malaysian data centers during 2027 and 2028, including new campuses in Selangor and Negeri Sembilan.
  • AMD’s third-quarter revenue rose 45% to $13.38 billion, and data center sales nearly doubled to 64% of the total.
  • Nvidia is reportedly in talks to guarantee more than $5 billion of debt for an Nscale building leased to Anthropic in West Virginia, according to The Information.
  • Drax, Brookfield and Radiant plan a data center campus at the Drax Power Station that they say could draw more than GBP 20 billion of investment, subject to planning and grid approvals.

The Big Story

For two years the main limits on AI construction were chips and power. Tuesday’s US election added a third: local voters. There were 41 data center measures on ballots across 10 states, and 21 of them were in Ohio, Fortune reported. Voters in at least 14 Ohio municipalities passed bans or other restrictions, and 10 of them passed outright bans, according to unofficial results compiled by The Columbus Dispatch. The margins were wide. Trenton banned data centers using more than 25 megawatts by 80% to 20%, a vote organizers hope will keep out a planned 18-building Amazon Web Services campus. In Piqua, where Meta had planned a data center, a similar charter ban passed with 66.7% and voters recalled three city commissioners. Grove City approved, with 55%, a rule requiring a public vote on developments that use more than 20 megawatts. Other governments are taking a different approach and setting conditions in exchange for speed. The UK’s new Data Centre Covenant sets a target of 6 gigawatts of AI data center capacity by 2030. Projects that meet its tests on water, energy costs and community benefits can get reserved or reallocated grid connections through a new ministerial unit. Malaysia welcomed Google’s $15 billion commitment, which comes with 1 gigawatt of clean energy capacity for the national grid and $160 million for shared water infrastructure near the planned Negeri Sembilan site, DCD reported. The result is a market where location depends more on politics than on the supply of land. Developers that can show what a community gets in return will have more sites to choose from.

AI

The chip companies are still reporting strong demand. AMD’s data center revenue reached about $8.5 billion in the third quarter, up 97% from a year earlier. The company forecast about $17 billion of total revenue for the fourth quarter, above analyst estimates. Lisa Su said she expects server revenue to double in 2027 and that AMD has secured the wafers, packaging and memory to support it, CNBC reported. Nvidia is also using its balance sheet to support demand. According to The Information, it is in talks to guarantee more than $5 billion of debt covering power and construction for a 460-megawatt Nscale building at the Monarch campus in West Virginia, which will run Vera Rubin systems for Anthropic. Nothing has been signed.

Money

Lenders outside the US are still writing large checks. Princeton Digital Group secured about $1.3 billion of green financing from six banks for its 200-megawatt JH1 campus in Johor, part of a plan to raise up to $5 billion of debt across Asia Pacific. Pure DC signed a $780 million growth facility with a $1.1 billion accordion, which brings its financing over the past 12 months to more than $6.2 billion. The Drax project is at an earlier stage. A Brookfield-Qai joint venture would back the site, with an initial GBP 2.5 billion for a first phase of up to 100 megawatts targeted for early 2028. That phase still needs planning approval, network approvals and a tenant.

Energy & Power

Grid queues remain long, and some operators are building their own generation. The New York Times reported that some AI campuses are running natural gas turbines converted from retired jet engines, including eight units installed for xAI’s Colossus 2. A Rystad Energy analyst said these units can bring a site online in about 24 months, TechCrunch noted. In the UK, Ofgem says data center developers have requested 72 gigawatts of connections, compared with national peak demand of 45 gigawatts last year, the BBC reported. Forecasts are moving too. PJM’s revised backstop procurement, filed with FERC, was designed to cover a 6.8-gigawatt shortfall, but Jefferies analysts estimate it could fall to about 630 megawatts after utilities cut their large-load forecasts. A separate Charles River Associates analysis still projects an 11.5-gigawatt gap by 2030, Utility Dive reported. In China, Envision says its Galaxy AI campus in Ulanqab is now running live workloads on an 800-volt DC power system, a claimed first. It has not disclosed the system’s capacity.

Government Power

The UK’s offer of faster grid access has a carbon cost. The covenant allows temporary on-site generation, but only for exceptionally strategic projects. A BBC investigation found four planned hyperscale sites considering gas power that, running at full capacity, could emit an estimated 4.1 million tonnes of carbon dioxide a year. In the US, Virginia’s new rules on generator permits take effect today. On November 9, the Senate is scheduled to hold a cloture vote to begin debate on a bipartisan permitting package that would require large data centers to pay for both existing and new transmission. The bill is still in its early stages.

Startup and Small Business Signal

Smaller companies are still finding capital. Applied Compute raised $350 million at a $3.25 billion valuation in a round led by Elad Gil, with participation from Nvidia. The training and inference startup says its annualized revenue has passed $100 million, and it plans to spend the money on more infrastructure. NexGen Cloud closed a $106 million four-year loan through USD.AI to finance 1,728 Nvidia B300 GPUs in Finland. All of that capacity is already contracted under a take-or-pay agreement.

AMP2 Bottom Line

Capital, chips and power equipment are all still available. Permission is getting harder to secure, and in a growing number of places it now goes to the projects that offer the most in return.

What AMP2 is watching next

  • Certification of Ohio's data center ballot results and any legal challenges to the bans.
  • The Senate cloture vote on the permitting package scheduled for November 9.
  • Whether Nvidia and Nscale sign the debt guarantee for the Anthropic building.
  • How large PJM's backstop procurement is once it recalculates the shortfall.
  • Planning consultation and a tenant for the first phase at Drax.