AMP² Daily Brief – October 31, 2026

AI. Money. Power.


The Giants Take Outside Money

Microsoft priced $25 billion of bonds a day after Meta lifted its stock sale to $97.5 billion. The largest buyers of AI capacity now raise outside capital as well, and the neoclouds below them are asking suppliers to back their debt.

Today’s Signals

  • Microsoft priced $25 billion of notes in 10 tranches maturing from 2028 to 2066, and expects the sale to close on November 4.
  • Microsoft’s quarterly capex of $45.2 billion came in under the $50 billion it had projected, and its CFO blamed delays at third-party GPU providers.
  • Meta raised its planned equity raise to $97.5 billion, including $25 billion of common stock priced at $625 a share.
  • Australia’s energy minister asked the market rule maker to require large data centers to contract new firmed power, with forced demand cuts as a possible penalty; it is a request, not yet a rule.
  • Thailand’s data center policy committee endorsed a draft framework that sorts sites into seven tiers by power use, and it now goes to the Cabinet.

The Big Story

This quarter the hyperscalers stopped paying for AI only out of operating cash. Microsoft, the one member of the group still reporting positive free cash flow, priced $25 billion of notes on Thursday. Its free cash flow fell 27% to $18.63 billion, CNBC reported, and CFO Amy Hood told analysts the company had access to the debt market but had not yet used it. Oracle announced plans for $10 billion of new debt the same week. Meta went to equity. It raised its planned offerings to $97.5 billion, Reuters reported, with $25 billion of common stock at $625 a share, $12.5 billion of mandatory convertible preferred, and a program of up to $60 billion to sell shares over time once its new Class C stock begins trading in early 2027. Nvidia, AMD and Broadcom have expressed interest in buying up to $5 billion of the stock. TechCrunch, citing S&P Global Market Intelligence, said Microsoft, Alphabet, Amazon, Meta and Oracle have raised a combined $326 billion of debt in 2026. Below the giants, a supplier may carry the risk. Nvidia is in talks to provide a residual value guarantee on Nscale’s debt for its West Virginia campus, The Information reported and Bloomberg corroborated, according to TechCrunch. If Nscale defaulted on construction payments, Nvidia would take over the facility temporarily and help find a buyer and tenant. Anthropic has a $44.6 billion contract for the first 460-megawatt building, according to Nscale’s IPO filing. Nothing is signed. Nvidia has extended about $170 billion of investments and credit support to neoclouds and large customers, The Information reported.

AI

Microsoft’s capex miss came from supply rather than a pullback. Hood said delays at third-party GPU providers will push some capacity into the first half of 2027, and Microsoft trimmed its 2026 capex forecast to $170 billion from $175 billion. Shares of CoreWeave, Nebius and IREN fell after the reports, CNBC said. Oracle said it will offer Google’s TPUs, starting with the eighth-generation 8t and 8i chips in 2027, along with OpenAI’s Jalapeno chip on its cloud, according to CNBC as summarized by TheDayAfterAI. It is the first time Google’s custom chips will run on another hyperscaler’s cloud. OpenAI separately plans to buy Google TPUs, The Information reported; neither company has confirmed it. Samsung’s quarterly operating profit topped 100 trillion won, with its chip business contributing 106.5 trillion won on demand for AI memory, including HBM4. Anthropic’s S-1 says it depends heavily on TSMC chips made in Taiwan and flags the risk of disruption.

Money

Neocloud lending now looks for collateral and contracts. Iren closed a $363 million equipment financing from six lenders led by Eldridge Capital Management and Silver Point Capital, secured by its GPU servers and backed by multiyear customer contracts. Hyderabad-based AM Intelligence plans to raise up to $3 billion in bonds and loans to buy Nvidia Rubin GPUs, Bloomberg reported, and expects $300 million in advance payments from potential customers. It is a plan, not a closed deal. The price of unsecured money is high. CoreWeave’s unsecured bonds yielded near 15% earlier this month, CNBC reported.

Energy & Power

Grid builders are asking the biggest loads to pay for the lines. AEP will start the Piketon transmission project in Ohio next year: three 765-kilovolt lines of about 3.2 gigawatts each, targeted for service at the end of 2028, 2029 and 2030, for SB Energy’s 10.4-gigawatt campus. SoftBank and its affiliates will pay for the lines. Georgia’s Public Service Commission approved a three-year pilot on October 27. From January 1, 2027, new Georgia Power customers seeking at least 100 megawatts generally face a 15-year minimum commitment and financial security requirements. Australia shows the scale problem. The market operator counts 225 data center projects with 67 gigawatts of combined capacity, against about 77 gigawatts of generation in the national market. Minister Chris Bowen asked the Australian Energy Market Commission to require qualifying sites to contract new firmed supply in the same region, with penalties and possible forced demand cuts for those that fall short. The commission has not yet started either rule change.

Government Power

Governments are writing entry terms. Britain’s Treasury published a Data Centre Covenant on October 28 setting standards for security, energy costs, water and local benefits, with faster grid connections and planning for strategic projects. A draft planning policy for large data centers is open for comment until January 8, 2027. Thailand’s draft framework defines data centers, sets minimum site and connection requirements, sorts sites into seven tiers from under 0.5 megawatts to 200 megawatts or more, and would accept investment proposals in rounds through a one-stop approval service. It still needs Cabinet approval. In North America, NERC has petitioned to register sites of at least 50 megawatts connected at 100 kilovolts or more, which it estimates would cover about 86% of projected computational load by the end of 2027. Malaysia’s customs department seized 30 servers with advanced AI chips in a suspected export-control case.

Startup and Small Business Signal

Georgia’s rule means smaller developers seeking 100 megawatts or more will need balance sheet or credit support before a utility builds for them, so partnering with a well-capitalized sponsor or phasing a project gets more attractive. Australia’s request favors local solar, storage and demand response providers who can sell firmed contracts to data centers in the same region. Britain’s consultation runs to January 8, and smaller firms in the supply chain can comment. Iren’s deal shows that GPUs already deployed under customer contracts can be refinanced to free up cash.

AMP2 Bottom Line

The AMP2 read: the four largest spenders can still borrow cheaply, and they are doing it. Smaller builders pay more or need a supplier’s guarantee, and regulators from Georgia to Canberra are making large loads post security before the grid expands for them.

What AMP2 is watching next

  • Closing of Microsoft's $25 billion bond sale on November 4.
  • Whether Nvidia signs a guarantee for Nscale's West Virginia financing.
  • Apple's results on November 2 and any change to its capex budget.
  • Whether Australia's market commission formally starts the data center firming rule change.
  • Thailand's Cabinet decision on its data center framework.
  • Comments on Britain's draft data center planning policy, due January 8.