The Chips Showed Up Before the Power
Amazon is warehousing billions of dollars of Nvidia racks until its sites can be energized, and Google is paying an Arkansas utility to build the batteries and lines its next phase needs. Getting power on time now costs real money.
Today’s Signals
- Amazon took early delivery of about $5 billion of Nvidia GB300 server racks before some of its sites had power, and expects about $3 billion more a month, according to internal emails reported by Business Insider.
- Google will cover about $600 million of batteries, substation work and transmission lines plus a 440-megawatt solar contract for its West Memphis campus, Entergy Arkansas said, pending state approval.
- Denmark’s new grid rules took effect on October 19 and put most data centers in the lowest of four priority categories when capacity is short.
- Tenstorrent raised a $1.5 billion Series E at a $6.2 billion valuation to expand production of its Galaxy server systems.
- Loudoun County deferred its vote on a pause of up to 12 months on data center and substation applications to November 17.
The Big Story
The hardware is arriving faster than the electricity. Amazon has set up an Early Rack Receipt program to take delivery of about $5 billion of Nvidia GB300 racks at US facilities before final deployment, and expects to accept about $3 billion more each month, according to internal August emails obtained by Business Insider. Some of that equipment is sitting in intermediate warehouses because several AWS sites lack the utility capacity to switch it on. Amazon called the staging a routine best business practice and disputed suggestions that it lacked a path to bring the sites live. That matters for cash. Amazon now owns the racks earlier, before they earn rental revenue, while it projects about $220 billion of capital spending this year and swung to negative free cash flow last quarter for the first time since 2023. The same gap cost Nscale a customer. Microsoft ended its agreement to anchor Nscale’s Loughton site in England after grid officials said they did not expect to supply power until the 2030s, Reuters reports. Nscale says it is still committed to the project and is looking at other power sources. Google is paying to close the gap ahead of time. Entergy Arkansas said Google will cover about $600 million of planned investment for a second phase at West Memphis: 1,000 and 400 megawatt-hour battery systems, a larger substation, two new 230-kilovolt lines and a 440-megawatt solar purchase agreement. Entergy says other customers will save at least $500 million over 20 years. The Arkansas Public Service Commission still has to approve it, with service expected in 2028. The companies that pay for the grid, or find their own power, will be the ones whose GPUs earn revenue first.
AI and Data Centers
Cloud providers are lining up capacity well ahead of delivery, mostly through non-binding paper. Nebius signed a letter of intent to buy a large block of compute from Volt’s planned Rotterdam campus, which would hold up to 250,000 GPUs across 600 megawatts at full build, Tech Times reports. Construction is not expected before 2027, and pricing and timing are still being negotiated. In Asia, Singapore-based Aolani signed non-binding letters of intent for up to 500 megawatts in Malaysia from the second half of 2027, which would take its committed Malaysian capacity to as much as 580 megawatts, up from about 80 this year. Chip challengers are still raising money too. Tenstorrent, led by chip architect Jim Keller, raised $1.5 billion at a $6.2 billion valuation, with Tether Capital among the investors, and counts Samsung and LG as customers. The open question is how much of this capacity gets power on the dates in the letters.
Money
Governments are using public incentives to pull capital toward domestic capacity. Turkey broke ground on a data center outside Ankara built by Ronesans Holding and Digital Realty. The first phase has more than 22 megawatts of IT capacity and costs $450 million for infrastructure plus $900 million for cooling and IT equipment, and Industry Minister Mehmet Fatih Kacir said the full site would reach $4.1 billion. The partners plan more than $10 billion across Ankara and Istanbul for about 200 megawatts, The Turkish Post reports. Venture money is following the same constraint. US startups working on AI data center power and compute raised $33.5 billion by early October, nearly double the 2025 total, Morgan Stanley said, with more than 80% going to power supply or compute efficiency per unit of electricity. The bank warned that the test will move from capital raised to capacity deployed.
Energy & Power
Some developers are skipping the congested part of the grid. Volt plans to draw power for its Rotterdam campus from North Sea offshore wind at the Maasvlakte landfall with Eneco, bypassing the congested Dutch inland network, and its CEO Han de Groot has said concerns about electricity are justified. Denmark is formalizing who waits. Rules effective October 19 rank households, smaller businesses and critical functions first, then green transition projects, then storage, with most data centers last. Grid operators must reject some data center requests when capacity is short, and projects that accept flexible connection terms can improve their standing. Requests of 3 megawatts or more go through regional rounds at least twice a year. For developers, flexibility is becoming a way to move up the queue.
Government Power
Cost protection for other ratepayers is the main argument in front of regulators. Colorado’s Public Utilities Commission begins several days of hearings on Wednesday on Xcel Energy’s proposed large-load tariff for data centers, The Colorado Sun reports. The most contested piece is a speed-to-market pathway that would let Xcel and a developer negotiate a confidential contract that could sidestep some of the tariff’s safeguards, which Xcel calls necessary flexibility and consumer advocates say could undermine the tariff. Local governments are moving at different speeds. Loudoun County in Virginia deferred its vote on a pause of up to 12 months on data center and substation applications to November 17 to give staff more time, the Loudoun Times-Mirror reports. Pettis County, Missouri approved a temporary moratorium on data centers covering at least 30 acres or worth at least $5 million.
Startup and Small Business Signal
Amazon’s warehoused racks point to a near-term service market. Hyperscalers and neoclouds holding GPUs ahead of power need secure staging, inventory tracking and fast installation crews ready when sites energize. Utility deals like Entergy’s create work for firms that model battery sizing and substation upgrades a large customer is paying for. Denmark’s flexible connection terms reward controls that can cut a site’s load on request.
AMP2 Bottom Line
The AMP2 read: buying GPUs is now the easy part. The scarce asset is a date when the power arrives, and buyers are paying for it with warehouses, batteries and transmission lines. Watch which projects sign power before they sign for chips.