Breakthru Ventures AI

AMP2

AI · Money · Power

What matters today at the intersection of artificial intelligence, capital, energy and government.

Daily Brief Published 7:05 AM

AMP² Daily Brief – November 7, 2026

AI. Money. Power.


The Grid Bill Comes Due

Days after a midterm vote that turned against data centers, three large US utilities told investors their growth plans are intact: Duke kept a 15.4-gigawatt large-load pipeline and a $103 billion plan, Sempra flagged a roughly 20% lift to Oncor’s capital plan, and DTE raised its five-year plan to $44.2 billion. The live question is who pays. Google answered in Wyoming with its own fuel-cell plant, while Illinois consumer groups put a possible $2 billion gap on ComEd’s data-center hookups.

Today’s Signals

  • Duke Energy said its 15.4-gigawatt large-load pipeline is virtually unchanged since the first quarter, with 7.8 gigawatts under signed service agreements, as it keeps a $103 billion spending plan after the midterms.
  • Sempra expects Oncor’s $47.5 billion five-year base capital plan to rise about 20% in its next update, after the Texas utility set a record 33.3-gigawatt peak.
  • DTE Energy raised its 2027-2031 investment plan to $44.2 billion and agreed to sell its non-utility DTE Vantage unit for $3 billion, with closing expected in the first half of 2027.
  • Google confirmed a $17 billion first data center in Wyoming, anchored by a 702-megawatt AEP fuel-cell plant with carbon capture under a 20-year power purchase agreement.
  • ComEd regulatory filings put the cost of connecting 30 data centers to its Illinois grid at $3.1 billion, against $721 million in developer deposits so far.

The Big Story

Tuesday’s vote shifted the politics of AI data centers. This week’s utility earnings calls showed how little it has shifted the capital plans, at least so far. Duke Energy CEO Harry Sideris said the company sees no change in its focus after a “historic” election night. Its large-load pipeline sits at 15.4 gigawatts, 7.8 gigawatts of it signed, and Duke plans more than 10 gigawatts of new gas generation and 4.8 gigawatts of batteries by 2031. In Texas, Sempra expects Oncor’s $47.5 billion base plan to rise about 20%, though Oncor CEO Allen Nye said it is “too soon to tell exactly” what the election means. In Michigan, DTE’s new five-year plan is $44.2 billion, up from $34.5 billion in the prior plan, with a 5-6 gigawatt large-load pipeline behind its 1.4-gigawatt Oracle deal and 1-gigawatt Google approval. What changed is the bill. Each of these executives framed growth around large loads paying their fair share, and the pressure to prove it is local. In Illinois, ComEd’s own filings show $3.1 billion in connection costs for 30 data centers and $721 million in deposits. Consumer groups see a possible $2 billion shortfall landing on household bills; ComEd counters that $1.1 billion of transmission costs is backed by 10-year transmission security agreements. The case is still open. The pattern is now visible from Detroit to Johor: the next gigawatt gets approved where that arithmetic is settled first.

AI

Reuters reports that about 600,000 Nvidia H200 chips are sitting in Hong Kong awaiting shipment to China while Beijing withholds approval for large-scale imports, citing people familiar with the matter. Several major Chinese internet companies have each obtained about 10,000 H200s, and an eight-card H200 server was offered for more than 6 million yuan, about $900,000, by the end of October, roughly triple its price a year earlier. Nvidia is also reportedly requiring Southeast Asian cloud providers that apply for Nvidia Cloud Partner status to enroll in its Fleet Intelligence GPU-tracking program; it has not said whether existing partners must join. On the hyperscaler side, Microsoft requested network-design changes at the 200 megawatts IREN is building for it in Texas. IREN pushed its target of more than $4 billion in annualized run-rate revenue to January, possibly the end of February.

Money

Utilities are reshaping balance sheets to fund the load. DTE says the $3 billion DTE Vantage sale reduces its equity and debt needs, and Duke has secured about one-third of the $10 billion in equity it plans to issue. Customers are still committing. IREN reported capital commitments of $18.95 billion at the end of September, up from $13.81 billion three months earlier, and expects about $15 billion of capital spending over the rest of its fiscal year. Google’s Wyoming campus is a $17 billion commitment, and AEP plans to invest about $4 billion in the fuel-cell plant serving it.

Energy & Power

Google’s Wyoming design is a working template for on-site supply. Bloom Energy solid-oxide fuel cells, owned and operated by AEP, will run on natural gas, with most of the carbon captured and stored at Tallgrass’s Eastern Wyoming Sequestration Hub. The campus will also take power from gas generators run by Tallgrass and Black Hills Energy, and Google is studying whether Tallgrass’s combined-cycle turbines can be fitted with carbon capture. The fuel-cell plant is due to be fully operational by the end of 2028, campus construction is slated to finish by 2031, and the site will be air-cooled. The same strain shows up in Southeast Asia. Wood Mackenzie estimates data centers already use 24% of Johor’s power, possibly rising to 40% by 2035, and Thailand’s energy minister has called for a separate, higher-tariff electricity category for data centers.

Government Power

Texas regulators are measuring the queue before writing rules. ERCOT’s preliminary data-center survey drew responses from 433 of 465 loads, covering about 177 gigawatts of requested interconnection, with a final report targeted for December 10. The San Antonio Express-News reports ERCOT is also probing whether developers are sizing projects just below its 75-megawatt large-load threshold to avoid review. Asia is tightening too. Thailand paused construction on 49 projects and approval decisions on 117 more in September; the Guardian reports Indonesia is also tightening. Canada is leaning in. Thursday’s federal budget proposes backstops and offtake agreements to help create 500 megawatts of new compute capacity. In the US, all but one of 41 data center-related ballot measures this week went against data centers, according to Ballotpedia figures cited by Reuters.

Startup and Small Business Signal

Ottawa’s plan targets a small-company problem. Ali Asaria, CEO of Toronto startup Transformer Lab, told the Globe and Mail he had unsuccessful conversations with more than 50 compute suppliers in recent weeks, as large buyers lock up specialized chips with long-term commitments. In Korea, Kosdaq-listed XIIlab is issuing a 10 billion won zero-coupon convertible bond, 8 billion won of it taken by National Growth Fund sub-funds, to fund AI data-center construction. And Core Scientific shows where former bitcoin miners are landing: third-quarter colocation revenue rose to $215.4 million, with 485 megawatts billing.

AMP2 Bottom Line

AMP2 Bottom Line: The election changed who gets a say, and the utilities answered with capital plans that held steady. The contest now is cost allocation, decided case by case in deposits, tariffs and long-term contracts. Projects that bring their own power or pay their connection costs up front should clear first. Projects that lean on shared rate bases will wait for regulators.

What AMP2 is watching next

  • ERCOT's final data-center survey report, targeted for December 10, and any rule change for loads under 75 megawatts.
  • A possible North Carolina large-load tariff settlement approval for Duke Energy by mid-November.
  • Illinois regulators' handling of ComEd's proposal to assign connection costs directly to individual data centers.
  • Oncor's updated five-year capital plan and the size of the expected 20% increase.
  • Whether Beijing clears larger H200 import volumes from the Hong Kong stockpile.
  • IREN's Microsoft deliveries against the January target.
  • Closing of DTE's $3 billion DTE Vantage sale, targeted for the first half of 2027.