AMP² Daily Brief – November 1, 2026

AI. Money. Power.


Trillions Committed, Megawatts Pending

The five largest AI spenders have lined up more than $3 trillion of future commitments, Bloomberg reported. Grid operators and regulators from California to Israel spent the week deciding who gets power first, and on what terms.

Today’s Signals

  • Alphabet, Meta, Microsoft, Amazon and Oracle have committed more than $3 trillion to future data center leases, equipment and energy, Bloomberg reported.
  • California’s grid operator approved a flexible interim hookup for large loads by a 5-0 board vote and will file it with federal regulators by November 16.
  • Israel’s Electricity Authority proposed capping each new data center at 200 megawatts after developers requested 27,000 megawatts of connections; the full decision goes to public consultation.
  • Britain confirmed it will give strategic projects priority in the grid queue, and its energy regulator is consulting on a data center commitment fee of GBP 237,500 to GBP 712,500 per megawatt.
  • Intel’s data center and AI revenue rose 78% to $7.3 billion, and the company says server CPU demand still exceeds supply.

The Big Story

The money side of the AI build-out is now measured in trillions. Alphabet, Meta, Microsoft, Amazon and Oracle have committed more than $3 trillion to future spending on data centers, leases, equipment and energy, Bloomberg reported, according to Silicon Report. About $1.3 trillion of that is future leases, some running 30 years, and $1.9 trillion is equipment and other orders. Alphabet alone has committed more than $1 trillion, nearly eight times its total a year ago, and Meta more than $800 billion. Amazon said it expects to spend meaningfully more in 2027 than the roughly $220 billion it plans this year. Research firm SemiAnalysis expects the US to add more than 50 gigawatts of data center capacity in 2027, with nearly half already at an advanced stage of construction and $1 trillion in leases signed, Axios reported. Power is arriving more slowly. In the week of October 18 to 23, developers proposed 2,795 megawatts of new campuses in Britain and Spain, and only 90 megawatts, about 3%, has grid access stated for 2029 or earlier, DC Market Insights calculated. Microsoft ended its plan to anchor Nscale’s site at Loughton, England, after the local network operator said the connection would not be ready on time, City AM reported. Spending plans still exceed the power that can be connected. The rules written this week decide which projects connect first.

AI

Chip supply is still tight below the GPU layer. Intel’s data center and AI revenue rose 78% from a year earlier to $7.3 billion. Server CPU demand exceeds supply, and Intel expects constraints to last into the first half of 2027, according to Central Intelligence’s summary of the results. Cloud capacity keeps spreading across Europe. Alibaba Cloud opened an Amsterdam region with two data centers, part of the $53 billion it has committed to AI and cloud infrastructure. CoreWeave said most of its 22.5 megawatts at atNorth’s DEN01 site in Denmark is now online.

Money

Buyers are paying for connected power. KDDI and Telehouse completed the purchase of an estate at East India Dock in London for more than GBP 220 million. The site comes with 65 MVA of secured power, which works out to about GBP 3.4 million per MVA, according to DC Market Insights. Equity is following contracted assets. Digital Realty reported $855 million of quarterly bookings and more than $1.4 billion of initial equity commitments for a strategy that holds stabilized hyperscale facilities. Its 1.5-gigawatt construction pipeline is 63% pre-leased, Central Intelligence reported. In the Gulf, capital is not the constraint. The Middle East has 1.6 gigawatts of live capacity, 2.6 gigawatts under construction and 13.8 gigawatts planned, according to JLL figures cited by Reuters. Saudi Arabia has more than $100 billion of projects planned through 2030, and those are plans, not financed builds. “Funding is rarely the limiting factor,” JLL’s Mathur told Reuters. Smaller operators are still looking for lenders. Hyperscale Data hired Newmark to find long-term debt for its Michigan campus and stated that no financing has been secured.

Energy & Power

Grid operators are writing terms for interim power. The California ISO board voted 5-0 on October 28 to approve a flexible interim load interconnection, which lets large loads connect before network upgrades are finished, provided they accept limits on how much power they draw based on grid conditions. The proposal also requires hourly forecasts and telemetry, and protocols for remotely disconnecting large loads when reliability requires it. It answers a June federal show-cause order and goes to FERC, the US federal energy regulator, by November 16. Israel shows what happens when requests exceed supply. Developers have asked for 27,000 megawatts of data center connections against 18,800 megawatts of installed generation, CTech reported. The Electricity Authority proposes a 200-megawatt cap per new site and a guarantee of 2 million shekels per megawatt. It is a proposal, with a three-week consultation. In Britain, Ofgem is consulting on a commitment fee equal to 2.5% to 7.5% of average project capital spending to discourage speculative grid requests, Computer Weekly reported.

Government Power

Governments are choosing which projects connect first. Britain’s energy department said on October 28 that it will reserve and reallocate grid capacity for strategically important demand, including data centers, in time for the next application window. It will align data center connections with regional targets after 2030, and it has not committed to auctioning demand capacity. Britain estimates it needs 6 gigawatts of AI data center capacity by 2030, and a new Ministerial Control Centre chaired by the AI minister will oversee delivery. Spain sent a revised data center decree to its Council of State on October 26. The rules would apply from 10 megawatts instead of 1 megawatt and keep an 80% requirement for new renewable power matched hour by hour. The government reportedly wants it approved before the November 29 election. In the US, more than 300 local moratoriums are in place, and SemiAnalysis says a New York executive order pausing environmental permits for larger facilities has delayed nearly 1 gigawatt, Axios reported.

Startup and Small Business Signal

For smaller developers, a confirmed grid date is now worth more than the land. A site with secured power in London sold for about GBP 3.4 million per MVA, and Britain’s proposed fee would charge speculative applicants up front. California’s interim service favors loads that can cut their draw on request, which opens work for battery, controls and demand-response providers. In Israel, anyone planning above 200 megawatts should prepare to shrink the project or split it into smaller sites.

AMP2 Bottom Line

The AMP2 read: the largest buyers have committed the capital, and regulators now decide which projects get power first. Developers with firm connections, flexible loads or signed tenants can raise money. Projects that have only an announced size will have a harder time.

What AMP2 is watching next

  • California ISO's large-load filing with FERC, due November 16.
  • Germany's grid connection package, with Bundestag readings expected November 9 to 13.
  • Israel's consultation on the 200-megawatt data center cap.
  • Whether Spain approves its revised data center decree before the November 29 election.
  • Ofgem's decision on the data center commitment fee.
  • Whether Amazon puts a number on its 2027 capital spending.