Gulf Money Goes Looking for Grid
Gulf investors put their names on AI data center plans in Oman, Spain and Greece this week. The money is committed early. Grid permits and paying tenants are arriving more slowly.
Today’s Signals
- An Omani consortium led by Mubbadrah Investment plans an AI data center of up to 400 megawatts with an initial $3 billion investment; Crusoe has indicated interest as an off-taker but has not signed.
- Oman-affiliated fund O-Green plans a EUR 7.4 billion, 570-megawatt campus near Zaragoza, Spain, but holds grid access permits for only 90 megawatts so far.
- Saudi Arabia’s HUMAIN plans up to 84 megawatts of Nvidia computing, including 50 megawatts for an unnamed U.S. client starting in mid-2027.
- Intel’s chief technology officer said chip tool output can probably grow about 2x, not 10x, and that tools ordered today take about 18 months to arrive.
- China’s draft technology export list adds 23 AI items, while its commerce ministry says API access to a restricted model does not count as an export.
The Big Story
Gulf capital is moving into AI infrastructure outside the Gulf, and the hard part now is getting it plugged in. In London on October 24, during Sultan Haitham’s state visit to the UK, Mubbadrah Investment said it is leading a consortium to build an AI data center in Oman of up to 400 megawatts, with an initial investment of $3 billion. O2 Global Energy will build 400 megawatts of solar with battery storage alongside grid supply. The tenant is the open question. Crusoe has indicated interest as a potential off-taker, and the consortium expects to sign a confirmation of that interest in the next few weeks. In Spain, Oman-affiliated fund O-Green and a local partner plan a EUR 7.4 billion campus at San Mateo de Gallego near Zaragoza, aiming for 570 megawatts on a site where Vantage had planned a EUR 3.2 billion project. Grid access permits cover 80 megawatts at Penaflor and 10 megawatts at Villanueva. Further requests are pending and would still fall short of 570 megawatts. The first 90-megawatt phase could go live in 2029. Abu Dhabi’s G42 signed memoranda with Greece’s Copelouzos Group to explore an AI factory, one of 18 agreements worth EUR 12.75 billion signed during the Abu Dhabi crown prince’s visit. No capacity or site was disclosed. Taken together, these are commitments of money. The megawatts behind them will depend on grid operators, permit offices and tenants who have yet to sign.
AI
Saudi Arabia is selling compute abroad as well as building it at home. HUMAIN’s expanded Nvidia plan covers up to 84 megawatts and about 27,000 GPUs. A first 14-megawatt phase of Blackwell B300 systems starts in the fourth quarter, and 70 megawatts of Vera Rubin follows from mid-2027, with 50 megawatts reserved for a U.S. client it did not name. The Vera Rubin portion is still subject to final agreements. Google Cloud said its A5X Vera Rubin instances will be generally available next month and can scale to 960,000 Rubin GPUs across multiple sites. Supply will grow more slowly than demand. Intel CTO Pushkar Ranade told the Dwarkesh Podcast that tool capacity can grow “not 10X, but probably 2X,” and said memory is tighter than compute.
Money
Equity windows are narrowing while lenders keep writing checks against specific assets. SK Hynix halted its review of a U.S. listing for Solidigm, citing concern from Korean regulators about dual listings, and its shares rose 4.4%. The company is still looking for ways to fund a new U.S. fab. TeraWulf lifted its Morgan Stanley revolver to about $400 million from $250 million and removed a $150 million letter-of-credit sublimit. Colocation is now entering the securitization market. KBRA assigned preliminary ratings to US Signal’s first data center asset-backed notes, secured by 10 facilities with $111.8 million of annual recurring revenue and 22.5 megawatts of critical load. Contracts have a weighted average of 2.1 years remaining, so the notes depend on renewals.
Energy & Power
Grid queues outside the U.S. are just as long. In Britain, 315 hyperscale data centers are waiting to connect to the national grid, requiring 73 gigawatts combined against a typical cold-winter peak of about 45 gigawatts, The Guardian reported. More than 100 planned UK sites aim to use gas turbines while they wait. In Indonesia, the Java-Madura-Bali grid can absorb only 3,207 megawatts of more than 12,000 megawatts of projected high-voltage data center demand through 2030, Asian Power reported. State utility PLN is weighing mobile substations and minimum consumption commitments in supply contracts. Flexibility is the main workaround on offer. BCG estimates flexible connections, where a site agrees to curtail at peaks, can cut connection waits to 2 to 4 years from 5 to 10 or more.
Government Power
China is writing rules for exporting AI. The commerce and science ministries opened a draft revision of the country’s restricted-export technology list on October 16 that adds 23 AI items, including large models, agents and computing clusters. The ministry says API, app and web access to a restricted model does not count as an export, while local deployment overseas would. DeepSeek and MiniMax have completed registration. The list remains a consultation draft. Malaysia plans a dedicated data center bill for Cabinet in 2027 to match growth to power and water supply. Local governments are still using pauses. Grand Junction, Colorado, approved a moratorium of up to one year on large data centers while it rewrites its rules.
Startup and Small Business Signal
Term sheets and memoranda are easy to announce, but off-take letters and grid permits are much harder to get. Advisers who can turn interest into a signed tenancy, or a 90-megawatt permit into a phased plan that lenders accept, will be in demand. Flexible connections need metering, controls and curtailment contracts that utilities trust. Short colocation contracts also mean renewal risk now sits inside bonds, which gives smaller operators with sticky customers a clearer path to financing.
AMP2 Bottom Line
The AMP2 read: Gulf capital is plentiful and patient, so it no longer decides which projects get built. Grid access and signed tenants decide that. Rank this week’s announcements by megawatts permitted and contracts signed, and most of the headline capacity drops out. Spain’s 90 permitted megawatts are a better guide to 2029 than the 570-megawatt target.