The Grid Wants Collateral
Israel, Minnesota and Indonesia are setting similar terms for AI power: post money up front, commit to pay for capacity and accept cutoffs when the grid runs short, while Nscale and Anthropic discuss another $45 billion of compute.
Today’s Signals
- Israel’s Electricity Authority published the main points of its data center connection rules: a 200-megawatt cap per new site and guarantees of NIS 2 million per megawatt requested.
- Nscale is in talks to sell Anthropic about $45 billion of computing power from a second West Virginia building, Reuters reports, citing a person familiar with the matter.
- Korea’s Elice Group traded 27% below its IPO price in its KOSDAQ debut on Tuesday after raising 201.1 billion won at the top of its range.
- Indonesia’s energy minister said data centers will need another 20 gigawatts, about a fifth of current national capacity.
- Loudoun County’s board votes Tuesday on a pause of up to 12 months on final votes for data center and substation applications, as a state senator proposes a three-year statewide moratorium.
The Big Story
Power systems want more than a developer’s word. In the past two days, three of them have shown similar terms for AI load: post collateral, commit to pay and accept cutoffs when the grid runs short. Israel went furthest. Its Electricity Authority published the main points of its connection rules on Sunday evening, after grid manager Noga received requests for 27,000 megawatts. New data centers would be capped at 200 megawatts each, with 1,000 megawatts of new allocation on top of about 2,000 already approved, Calcalist reports. Developers would post guarantees of NIS 2 million per megawatt requested, and sites would need backup arrangements so the grid can disconnect them during extreme demand. The full decision goes to a three-week public consultation and could still change. In Minnesota, Google is writing the commitment into its utility deal. Its proposed 780-megawatt Pine Island campus comes with 1,400 megawatts of wind, 200 of solar and 300 of batteries that Google would help pay for on Xcel Energy’s grid, CNBC reports. Google would pay for at least 75% of its contracted capacity even if it uses less, and would owe up to eight years of those minimum charges if it ended the agreement early. Minnesota regulators still have to approve it. Indonesia is planning from the supply side. Energy minister Bahlil Lahadalia said Monday that data centers will need another 20 gigawatts, about 20% of today’s national capacity, and that the government will ask investors for their site plans so power can be built to match. Britain’s regulator has proposed a refundable fee of GBP 237,500 to GBP 712,500 per megawatt for large data centers in its queue, with no final decision yet. A grid connection now comes with a deposit, a minimum bill and an off switch.
AI and Data Centers
The big model labs are still signing with neoclouds. Nscale is in talks to sell Anthropic about $45 billion of computing power from a second building at its Monarch campus in West Virginia, a person familiar with the matter told Reuters. The building would deliver 460 megawatts on Nvidia Vera Rubin chips, Anthropic would hold a right of first refusal on a third, and the details could still change. Bloomberg also reported that some investors have urged Anthropic to lower its IPO valuation target. Nvidia is also picking up business beyond the GPU. Modal, which rents compute to AI developers and raised $750 million at a $15.75 billion valuation last week, will add Nvidia’s Vera CPU to host AI agents after early tests showed it doubled agent throughput, Reuters reports. Nvidia has told investors it expects at least $20 billion of Vera sales this fiscal year.
Money
Public investors are still pricing AI infrastructure harshly. Korea’s Elice Group raised 201.1 billion won, about $151 million, selling shares at the top of its range, then opened 16% below the offer price on Tuesday and was last down 27%, Reuters reports. It follows pulled or paused listings from AirTrunk, Firmus and SB Energy. Firmus has turned to private money. After withdrawing an ASX listing that implied about $30 billion of value against roughly $51 million of annual revenue, it is seeking $2 billion to $3 billion from existing backers, Startup Fortune reports, citing Bloomberg. New platforms keep launching where demand is visible. Hillhouse-backed TeraNova DC plans more than 2 gigawatts in India by 2032, more than the country’s roughly 1.75 gigawatts operating at the end of June, according to CBRE, though it has disclosed no budget or first commissioning date.
Energy & Power
Developers are designing around the grid queue. Hitachi, Brookfield, Hartree and Tokyo Gas announced a memorandum of understanding for Japanese data centers that use on-site generation as the main power source, backed by batteries and grid power, with first projects planned in the Kanto and Kyushu regions. No capacity figure was given. Indonesia’s numbers show where some of that load may land. Batam already has 1.47 gigawatts of data center capacity available, committed or in development, and PLN Batam’s 450-megawatt supply contract with DayOne is the largest for a data center in the country, according to the energy ministry. In the US mid-Atlantic, the margin is thin. PJM has issued at least six maximum generation alerts this year, after 11 in 2025 and one in 2024, GridLab’s Cassady Craighill told Loudoun Now.
Government Power
Northern Virginia, home to the world’s largest concentration of data centers, is moving toward a pause. Loudoun County’s Board of Supervisors votes Tuesday on a resolution that would pause final votes on legislative data center and substation applications for up to 12 months, retroactive to September 15. State Sen. Russet Perry has filed a bill for the 2027 session that would impose a three-year statewide moratorium on local approvals and state permits for data centers and their power infrastructure. The Data Center Coalition opposes it, citing Loudoun’s $1.3 billion in annual data center tax revenue, while the Piedmont Environmental Council supports it. BlackRock’s Larry Fink told CNBC last week that a national pause on data center construction could push the US into recession.
Startup and Small Business Signal
The openings follow the new terms. Developers facing per-megawatt guarantees and minimum-payment clauses need capacity models that show how much load they can actually fill before they post collateral. Sites that must accept curtailment need controls and backup systems that can drop load on command. Builders of 25-megawatt sites can test Jigar Shah’s argument to CNBC that such sites can use spare capacity already on the grid.
AMP2 Bottom Line
The AMP2 read: grid access now comes with conditions written in money. Developers who can post guarantees, sign minimum bills and accept curtailment will get connected first. Everyone else waits in the queue or builds their own power.