Lenders Are Pricing the Wait
AI debt markets spent last week marking down projects whose power, permits or tenants sit years away, while TSMC says chip demand still outruns supply and Washington moves toward one rule on who pays for the grid.
Today’s Signals
- CoreWeave’s bonds slid last week as market pricing implied a better-than-60% chance it misses obligations on about $72 billion of liabilities, the New York Times reported.
- AirTrunk’s Singapore REIT, Firmus and SB Energy pulled or paused listings in the past week, Reuters reports, even as Asian data center M&A hit a record $21.3 billion.
- TSMC guided fourth-quarter revenue to $52.3 billion to $54.3 billion after a $46.7 billion third quarter and said AI chip demand still exceeds supply.
- A bipartisan Senate permitting bill would make data centers above 20 megawatts pay the grid costs their demand creates, and it is expected to clear the Senate after the midterms.
- Saudi Arabia’s Humain has opened bidding, due November 8, on a roughly $1 billion, 100-megawatt Riyadh build designed for 240-to-250-kilowatt racks.
The Big Story
Money hasn’t left AI infrastructure, but waiting got expensive. Bond investors marked down projects whose power, permits or tenants sit years away, and the discount is now visible in specific loans. CoreWeave is the loudest case. The neocloud carries about $72 billion in liabilities across 51 data centers, and as its bonds slid, market pricing implied a better-than-60% chance it fails to meet its obligations, the New York Times reported. Its shares bounced 5.9% later in the week as Treasury yields eased, so the market is still deciding how bad this is. Oracle shows how a schedule becomes a credit problem. Its Port Washington, Wisconsin, campus, Project Lighthouse, was meant to run by 2028 and help repay part of a $38 billion bank loan. State regulators have pushed back approval of the grid work it needs, researcher Aterio now sees operations unlikely before 2029, a year before the debt comes due, and some of that loan has traded around 90 cents on the dollar. Debt tied to Oracle’s New Mexico site, built by Blue Owl and still short of state power permits, has sold near 80 cents, people familiar with the trades said. The UK delivered the same lesson from the customer side. Microsoft ended its agreement for Nscale’s Loughton site, a planned 50 megawatts of Azure compute for early 2027, after UK Power Networks signaled enough power might not arrive until the early to mid-2030s. Nscale says the relationship remains strong and its other contracts are unaffected. A megawatt you can switch on next year is now worth more than two you might switch on in 2030.
AI and Data Centers
Upstream, the shortage runs the other way. TSMC reported $46.7 billion of third-quarter revenue, guided the fourth quarter to $52.3 billion to $54.3 billion, about 58% above a year earlier, and held 2026 capex at $60 billion to $64 billion. C.C. Wei said demand still exceeds supply. Buyers are hedging that bottleneck in software. A Meta paper describes training recommendation models on AMD Instinct MI350X GPUs against Nvidia B200, and reports that reworking models to use the MI350X’s larger memory lifted throughput by up to 1.5 times. The authors call it the first hyperscaler report of production AMD training at scale. Model labs are locking in capacity anyway. The Information reported that Anthropic has signed more than 15 gigawatts of leases across more than 10 clouds, worth about $530 billion, plus an IREN contract of undisclosed size. Every one of those leases depends on a site going live on time.
Money
Equity investors are drawing the sharpest lines. Blackstone-backed AirTrunk’s Singapore REIT, Nvidia-backed Firmus and SoftBank-backed SB Energy have pulled or paused listings in the past week, Reuters reported Sunday. Firmus had aimed to raise $5 billion while carrying about $30 billion of debt. Private deals are still clearing. Asian data center M&A has reached a record $21.3 billion, more than double 2025’s $10 billion, according to Dealogic, while loans and bonds for the sector total $22.3 billion and equity raising is down 4.6% at $5.4 billion. AirTrunk is nearing a sale of its Johor campus at about a $2 billion valuation to investors including Malaysian pension fund KWAP, and Bain has received final bids for at least 40% of Bridge Data Centres at a valuation near $5 billion, people familiar with the talks said. At the top of the stack, SoftBank is the bellwether. Insuring $1 million of its debt now costs more than $40,000, up from under $27,000 at the start of the year.
Energy & Power
Power density is now written into the tender. Humain, the PIF-backed AI developer, has issued an EPC request for a 100-megawatt facility in Riyadh’s Al-Saad district, with bids due November 8, two 50-megawatt stages and racks of 240 to 250 kilowatts on direct-to-chip liquid cooling, Meed reports. The contract is put at about $1 billion, inside a planned 6-gigawatt campus. Southeast Asia keeps adding capacity on paper. Singapore neocloud Aolani signed non-binding letters of intent for 500 megawatts across Malaysian sites starting in the second half of 2027. Inside the hall, GPU loads swing hard. Siemens led a round valuing Estonia’s Skeleton Technologies above $1 billion and will sell its supercapacitor systems to data center customers. Skeleton’s claim of up to 40% energy savings has not been independently tested.
Government Power
Washington is edging toward one federal answer on who pays. The Bipartisan American Affordability and Jobs Act would set permit deadlines, exempt more projects from long reviews and limit challenges, and it is expected to clear the Senate in the lame-duck session, Bisnow reports. Data centers above 20 megawatts would pay grid costs that would not exist but for their demand, beyond upgrades built only for them. Host Digital’s Harmol Samra called speculative upfront capex “a death knell.” Local governments are pausing instead. Florida’s Manatee County adopted a 12-month moratorium on new data center applications on October 8, and Virginia’s Loudoun County takes up a possible pause on Tuesday.
Startup and Small Business Signal
The openings are practical. Lenders and secondary buyers now trading project debt at a discount need independent, site-by-site diligence on power and permit timelines. Smaller developers facing cost assignment under BAAJA-style rules need early grid-cost models before they spend on a site. Builders specifying 240-kilowatt racks need liquid-cooling and power-quality contractors who can hit fixed energization dates.
AMP2 Bottom Line
The AMP2 read: capital is still funding AI infrastructure, and it now prices the energization date. Sites with firm power and signed tenants keep borrowing. Anything waiting on a grid, a permit or a listing pays more for money, or goes without.